What’s community wind got over those mega farms?
September 19, 2011 by Windpower Engineering
Filed under Community Wind Power, Construction, Wind Power Projects
Community wind refers to 100-kW to 100-MW projects owned in part by local community members, often land owners of the site. Though community wind represents only 4% of the overall wind market, it’s the fastest growing segment of the industry. The community-wind development model has several benefits over traditional absentee-owned mega farms.
Landowners often have a stake in the community-wind project, so they reap a higher return than in larger farms. The project also positively impacts the local economy through job creation, and the utility gains community good will. Also, zoning and permitting is often easier and faster when the application is submitted for a project that directly benefits the community—and when the community rallies behind it—than for one driven by outside developers and investors. Furthermore, the cost of transmission and connection to the grid can be much lower because projects can be closer to the cities they support, and require lower voltage lines with fewer upgrade costs to deliver power. To realize benefits, local partners must invest some capital, time, and effort, particularly in early stages. Most initial planning work must occur locally. Often there’s a steep learning curve at this point, because few laypeople have the specialized knowledge to determine if a project is viable.
The tricky part for any new wind entrepreneur is identifying a suitable location. Many factors will rule out a site altogether. One must consider environmental aspects, such as wetlands, bird-migration patterns, and protected animal habitats, as well as aircraft-flight patterns. Also, along with state and federal permits and regulations, local restrictions and ordinances mandate how close a turbine may sit to residential areas.
Once a site is identified, several factors help determine its economic viability, wind availability being foremost. While different turbines have different capacities, the total power the farm can be expected to produce depends on the expected average wind speed. The most efficient farms have an average wind speed of 15 mph or more, though that figure can fluctuate in relation to power cost in any given state. Next, assess the cost of turning the wind into electricity on the grid. This includes everything from purchasing and erecting the turbines, to grid connection, and cost offsets such as state and federal grants and tax credits. The final factor to consider is the local market price for energy. A wind farm is considered a viable project if it can produce enough energy so that, at market price, it will provide a reasonable rate of return to its investors.
After a site is found environmentally and economically viable, and adheres to all regulations, most initial work can be done from a desk. High-resolution maps, wind-resource maps, and overlays with information on transmission lines, protected areas, and even air patterns are available in digital format, on the internet, and through private companies. Acquiring this data is much quicker and easier than in the early days of wind farms, when a developer had to drive a truck over miles of windblown prairie.
Next, to measure the wind, a carefully positioned meteorological (MET) tower with wind gauges at various heights will record actual wind speeds and direction for six months to a year. Based on this data, a specialist can estimate the long-term average wind speeds at turbine height for each location. This determination, along with turbine specifications, helps a developer arrive at the farm’s total expected energy. Losses must be factored in, such as maintenance down time and “tower shading,” where one turbine blocks wind from another. Total expected energy is used to determine the expected financial return, and therefore the site’s potential viability. Then developers can focus on gaining permits, signing a Power Purchase Agreement with the local utility, and securing financing. Finally, construction can begin. While work can be accomplished relatively quickly in comparison with the project prep, wind-farm construction and connection is a complex task. In most cases, a special wind-development group will partner with local landowners to achieve the best results in the given conditions.
Community-wind projects make sense in many places throughout the country, but getting expert help to assess a site and partner in completing specialized tasks will help expedite the process and ensure getting a project across the finish line.
WPE
Cooling and controls let turbines generate more power
July 28, 2010 by KRemington
Filed under Wind Power News

The company provides direct drive, water cooled, permanent-magnet-AC generators coupled to a braking system. No gearbox means the design provides a low maintenance, high-efficiency generator.
Grid Tie Inverter software uses proprietary algorithms to increase the range in which sustainable energy sources can deliver 60-Hz ac to the power grid. “We estimate an increase in efficiency of up to 25%,” says Energetic Drives’ CEO Ian Griffiths of the company’s algorithms. “For example, a traditional wind turbine generator has to be turning at a sustained rate, from 1,200 to 1,800 rpm (depending on number of poles per generator), to produce useable electricity. Outside of that range, the power is called ‘dirty’ because it is inconsistent and unusable. The technology lets the wind turbine use it at a constant 120% of the generator rating with our cooling system employed. This development allows producing ‘clean’ power over a wider range of wind speeds, from 30 to 120% of the generator’s rating. The software also provides for a consistent flow of clean, synchronized, utility-power energy to the grid, compatible with IEEE 519 and 1547 certifications. It results in a dynamic tool for smart-grid compatibility.”
Windpower Innovations Inc, Queen Creek, Ariz, says its wholly owned subsidiary, Energetic Drives LLC has been unveiled as the “innovation division” of WindPower Innovations Inc. The company says that along with its other subsidiary, XH Industries, it will feature efficient proprietary gear-box designs, grid-tie components and electronics, and improvements to existing equipment.
Energetic Drives LLC
Korea manufactures turbines for remote mountain villages
May 27, 2010 by Kathleen Zipp
Filed under Turbine Design, Wind Power News
Hanjin Ltd., a Korean manufacturer in the petrochemical industry and palletizing systems, has produced the HJWT1500, a MW-class wind turbine. The 1500/70 horizontal-axis turbine features a three-bladed upwind rotor with pitch power regulation and constant rotor speed, an asynchronous generator coupled directly to the grid, and an active yaw system. The 1500/77 upgrade has a 20% larger area. The 1.5 MW turbine has a speed of 3.5 m/s and a cut out speed of 25 m/s. Friction sliding bearings provide easy maintenance and robustness against strong wind turbulence. Fluid coupling is adopted for the power quality grid code and the system protection from overload at grid fault. A fast pitch system also provides enhanced power control performance.
Hanjin also offers the HJWT100/20 turbine with stall power regulation and two constant rotor speeds. The turbine includes a controlled electro mechanical break rather than a previous tip brake for easier maintenance. There is no misalignment during load change because of the in-line drive train without the offset of high-speed shafts. The turbine is specifically designed for Korean domestic topology such as islands and remote mountain villages.
Hanjin
Hanjinind.co.kr
Soft brake for turbines
September 23, 2009 by Windpower Engineering
Filed under Mechanical Components, Yaw and Pitch Brakes
Before engineers access a nacelle and hub for maintenance, the rotor must be stopped and secured in a particular position. Today, an electrohydraulic brake control can provide a soft stop to the required position. Then hydraulic controls can engage a rotor lock.

Stopping a turbine by the drive train brake alone puts high torque on the gearbox. Doing so for service work generates undue strains and wear. Hence, Rexroth distinguishes between emergency and service brakes, so slowing a rotor to position requires a soft brake. Locking the rotor allows releasing the soft brake, eliminating loads otherwise acting on the drivetrain, a task that lengthens the service life of the wind turbine.
In addition, when wind direction changes, lowering the clamping pressure exerted by the soft yaw brake lets the yaw drive work. After reaching a new position, controls restore pressure to hold the nacelle in position.
Bosch Rexroth
www.boschrexroth.com


