By Maryruth Belsey Priebe
IQPC GmbH

Before the power generated at an offshore wind farm is fed into the transmission grid, it is combined in an offshore transformer substation, like the Siemens’ Lillgrund offshore wind park substation. Voltage there is converted from 33 kV (or now 66 kV is sometimes used) to a transmission voltage of 138 kV by a 120-MVA power transformer. Platform equipment also includes medium-voltage switchgear, protection and control technology, and a service transformer for the substation. (Credit: Siemens AG)
Offshore substations — the systems that collect and export the power generated by turbines through specialized submarine cables — are an essential component of offshore wind farms, especially at large, multi-megawatt sites. These systems serve an important function: to stabilize and maximize the voltage of power generated offshore, reduce potential electrical losses, transmit electricity to shore, and do so in a manner that supplies the greatest return on investment.
But the wind industry is still young, and there is a long way to go before the development of offshore substation systems fully mature. Given that the typical cost breakdown for large-scale offshore wind installations includes 7.5% for platforms, cabling, substation equipment, and more, there is opportunity for greater cost-effectiveness and efficiency.
Sizing up substations
Early substations for offshore wind farms consisted of simple topside frames with basic modules installed on top or as a covered deck. These structures were intended to operate unmanned, and required few visits from personnel. In many cases, these substations weighed as little as 400 tons.
That’s not much compared to today’s more advanced structures that weigh upwards of 10,000 to about 22,000 tons. These substations are more fully developed, and consist of a topside or a deck installed on monopole or jacket structures. Options today include self-floating and self-installing structures that eliminate need for expensive marine lifts or cranes.
Over and above serving as an offshore power-converter station, a substation’s platform may be equipped with boat landings, a helicopter deck (yes, a helicopter deck), accommodations, and act as a logistics’ service base during installation and operation of an offshore wind farm. Not surprisingly, one of the greatest cost challenges to developing an offshore substation is the sheer size of the structure. Much like transporting and installing wind-turbine components offshore, careful logistical planning is key.
The two substations installed at what’s been dubbed “the world’s largest wind farm at sea,” the UK’s London Array offshore wind farm, required use of a 3,300-ton, lift-capacity floating crane just to maneuver the systems onto a foundation that’s 15 km from shore — undoubtedly a costly venture.
With an area of around 20 x 20 m, the substations are each 22-m high, and feature three levels of structural steel decks. They weigh in at 1,250 tons and are supported on transition pieces, connected to monopile foundations driven into the seabed. The substations let the wind farm operate more efficiently by transforming the energy generated from 33,000 to 150,000V, after which electricity is exported through cables 50-km long to an onshore substation.
Self-installing structures
One option for overcoming the size and cost challenges related to substation installation is a self-installing platform, a design used by ABB and Alstom Grid. Their floating and self-installing HVDC offshore substation was used to connect the 400-MW, MEG 1 offshore wind farm to the German high-voltage, direct current system.

Alstom’s GIS substations were installed on a platform at the Baltic Sea 2 offshore wind site. The platform was placed on a pre-installed jacket and brought out to the installation site where water depths reached 44 meters. The buoyant and self-erecting platform design enabled a high degree of flexibility and independency from crane ships for the transport and installation of the substation. The closed platform layout protects the electrical components from offshore conditions. (Credit: Alstom)
According to Alstom, the platform uses a “suction can” method to set the foundations to the seabed floor and is fully self-contained to protect electrical equipment. The method reduces cost, noise pollution, and is believed safer on the environment when compared to conventional options.
Siemens is also working on a more efficient installation system for offshore substations. The company’s WIPOS (wind-power offshore substation) is available in different options, including self-lifting, topside and jacket, and floating, all of which involve pre-fabricated sections with flexible configurations for ac and dc applications.
Much like, Alstom’s system, Siemens’ self-lifting platform can self-install to reduce the need, costs, and risks related to heavy lift vessels. In this configuration, the foundation is the substructure base frame, which connects to piles that are driven into the seabed. The topside includes a rectangular pontoon with customizable internal walls and decks. Self-jacking legs, attached to the topside, are immersed and then connected to the substructure base frame.
Operations & maintenance
Configuration of a substation, its access points, and storage areas for maintenance equipment are important when considering the design for use at an offshore wind farm. These factors impact how often a substation may require servicing and its accessibility. But the factors are also difficult to assess because of extreme weather conditions and vibrations an offshore substation must endure, so routine O&M is typically a guess.
Because maintaining anything offshore is more costly and hazardous to operators, there is an inherent risk of unexpected equipment breakdown if maintenance is not made simpler and more efficient. The wind industry is responding to these challenges several ways. For example, along with using condition-monitoring systems, the industry is planning more frequent maintenance visits to detect potential equipment failures early on. They are also starting to take notes. With more detailed records, wind technicians can identify issues and that insight provides for better future substation designs.
Transformers, for example, are an issue. They the use oil as electrical insulation and are made of thin steel making them susceptible to corrosion. To overcome this challenge, designers are working with gas-insulated transformers that are safer for personnel to deal with. Additionally, some substation designs are moving transformers indoors to help minimize exposure to the elements.
Standardization in substation safety and manufacturing is another topic gaining traction. If the industry can develop more consistent standards for substation designs and installation techniques, time and cost savings are bound to follow. But this takes time. To date, just over 20 substations for offshore wind farms have been built around the world.
Filed Under: Offshore wind, Projects, Transformers
These sources of renewable energy are the future for many nations across the globe. Some of the global tech-based companies like Siemens, Honeywell are taking responsibility for the same by making powerful turbines and smart building solutions to make a building more energy-efficient.
What sort of electrical equipment is used on an offshore wind substation?
Enabling technologies for the ocean wave energy conversion industry which now has a performance advantage over wind turbines
Aw inspiring