The Nordex Group has received an order from an undisclosed international project developer in the United States.
Starting in the spring of 2020, the company will be installing a wind farm with 63, AW125/3150 turbines with a combined rated output of 198 MW. Nordex says that the order uses some equipment from a “safe harbor” transaction dating back to 2016.
Through the 5% Safe Harbor qualification, “Safe harbor” equipment purchased in 2016 can qualify customers’ projects for the 100% Production Tax Credit if placed in service by the end of 2020.
The company received advance payment for these components and produced them in the same year.